RECONSTRUCITION OF 6 kV SWITCHGEAR OF UNIT 7 IN TPP KAKANJ, B&H.

23.11.2013.

About project

Preparation of main design for replacing old control/protection devices, supervision of equipment installation, configuration of control/protection devices,testing and commissioning of 6 kV bays of Unit 7 in TPP Kakanj, B&H. In total 16 bays with control/protection devices Siemens SIPROTEC 4 7SJ62.

Contractor

Siemens Sarajevo

End-Client

EP BiH TE Kakanj, B&H